Angus L. Macdonald Bridge facts for kids
Quick facts for kids Angus L. Macdonald Bridge |
|
---|---|
The Macdonald Bridge in July 2015.
|
|
Coordinates | 44°39′49″N 63°35′05″W / 44.6637°N 63.5846°W |
Carries | Motor vehicles, pedestrians, and bicycles |
Crosses | Halifax Harbour |
Locale | Halifax Regional Municipality (Halifax — Dartmouth) |
Official name | Angus L. MacDonald Bridge |
Other name(s) | Macdonald Bridge The Old Bridge |
Maintained by | Halifax-Dartmouth Bridge Commission |
MMSI | 16261 |
Characteristics | |
Design | Suspension bridge |
Total length | 1.3 kilometres (0.81 mi) |
Width | 11.5 metres (34.8 feet) |
Height | 102.9 metres (337.69 feet) |
Longest span | 441 metres |
Clearance above | 54 metres (177.25 ft) at centre-span |
Clearance below | 46.9 metres (153.87 ft) at centre-span |
History | |
Designer | Philip Louis Pratley Henry Hugh Lewis Pratley Charles Nicholas Monsarrat |
Construction begin | 1952 |
Opened | April 2, 1955 |
Statistics | |
Daily traffic | 44,000 (2012) |
Toll | CA$1.00 cash/$0.80 MACPASS |
The Angus L. Macdonald Bridge is a suspension bridge crossing Halifax Harbour in Nova Scotia, Canada; it opened on April 2, 1955.
The bridge is one of two suspension bridges linking the Halifax Peninsula to Dartmouth in the Halifax Regional Municipality.
It is named after the former premier of Nova Scotia, Angus L. Macdonald, who had died in 1954 and had been instrumental in having the bridge built. The bridge was designed by Philip Louis Pratley, one of Canada's foremost long-span bridge designers who had also been responsible for the Lions Gate Bridge in Vancouver. The bridges have a similar design, which is most notable in the towers. The contractor was Dominion Bridge Company Ltd.
The bridge regularly experiences traffic congestion during rush hours as a result of the structure's proximity to the downtown cores of Halifax and Dartmouth, as well as its narrow width. Large commercial vehicles are not permitted to cross and must use the wider MacKay Bridge to the northwest. Public transit buses are allowed to cross and the bridge links several Halifax Transit routes. In 2014/15 the average number of vehicle crossings per month was 1,183,095.
As of 2015 the toll charge to cross for regular passenger vehicles is $1.00 cash or $0.80 with the MACPASS electronic toll system (60¢ tokens were once used but are no longer accepted as of May 1, 2008). The original toll, when the Macdonald opened in 1955, was 40 cents plus 5 cents per passenger. There was also a separate toll for trucks, cyclists, pedestrians, motorcycles and horses/rider.
History
Construction of the bridge took place between 1952 and 1955. Caissons were used for underwater work. Five workers died falling from catwalks during construction. The bridge opened on April 2, 1955, and originally cost $11.5 million.
1999 modernization
A modernization project was undertaken in the late 1990s and completed in 1999 which saw the original two lanes and one sidewalk and utility corridor expanded to three lanes, with the centre lane being reversible to assist with traffic flow during peak periods.
To reduce the weight of the roadway, asphalt and concrete were removed and special steel plating (an orthotropic deck) was used in its place. This deck is 35% lighter than the old one. New pedestrian and bicycle lanes were attached to the outside of the structure to replace the original sidewalks.
External aesthetic lights were added during the modernisation project which saw the bridge's towers lit for the first time on a continuous basis every evening from sunset until midnight. Critics derided the effort as a waste of electricity, given Halifax Harbour's frequent foggy weather conditions. The lighting was estimated by the bridge authority to cost in excess of $50,000 a year in 1999.
2015 "Big Lift" project
Beginning in 2015 another major renovation of the bridge started which saw the temporary removal of the pedway and bike lanes. At a cost of $150 million, every piece of steel that makes up the suspended spans, except the towers and two main cables, were replaced; the non-suspended approach spans remained. New vertical cables were required due to the relocation of the stiffening trusses from above deck level to below deck level. Construction mostly occurred overnight with the bridge open to traffic during the day, but many full-weekend closures were necessary. The replacement portion of the project was completed in February 2017.
After the Lion's Gate Bridge, this was only the second time that a suspension bridge had its suspended spans completely replaced while continuing to allow regular traffic flow during the daytime. Principal engineering work for the project was done by the same firm that managed the work on the Lion's Gate Bridge.
During the Big Lift project Halifax Transit continued to run its regularly scheduled conventional bus service across the Macdonald bridge, except during times when the bridge was closed. During scheduled closures, Halifax Transit operated a shuttle service using the MacKay Bridge.
Halifax Harbour Bridges also operated a free, 24-hour-a-day shuttle service during construction to accommodate the bridge's pedestrian and bicycle users. It operated on a load-and-go basis during the weekday morning and afternoon rush hours, and on a 30-minute schedule at all other times of the day and overnight.